Projects in the research area Environment

Hood Canal Bridge Expert Review
Research Area
Environment
Scheduled Completion Date
2016-06-30
Revised Completion Date
2016-07-31
Principal Investigator
Email Hallenbeck, M. E.
Research Manager
Email Brooks, Rhonda
Technical Monitor
 
Budget Number
63-2844
Rumble Strip Report
Research Area
Environment
Scheduled Completion Date
2014-07-31
Revised Completion Date
 
Principal Investigator
Email Hallenbeck, M. E.
Research Manager
Email Brooks, Rhonda
Technical Monitor
Email Berrends, Terry
Budget Number
66-8827
I-405/ Renton to Bellevue Stormwater
Research Area
Environment
Scheduled Completion Date
2016-07-31
Revised Completion Date
2016-09-30
Principal Investigator
James, Christopher Andrew
Research Manager
Email Saechao, Lu
Technical Monitor
 
Budget Number
63-5107
Twin study of environment, lifestyle behavior and health
Research Area
Environment
Scheduled Completion Date
2016-05-31
Revised Completion Date
 
Principal Investigator
Email Moudon, A. V.
Research Manager
 
Technical Monitor
 
Budget Number
63-4674
Reduction of Underwater Sound Levels from Pile Driving Operations
Research Area
Environment
Scheduled Completion Date
2009-12-31
Revised Completion Date
2014-07-31
Principal Investigator
Email Reinhall, Per
Research Manager
Email Brooks, Rhonda
Technical Monitor
Email Laughlin, Jim
Budget Number
63-5070
Measurement of Impact Pile Driving Noise from Prototype Piles, Vashon Trestle Seismic Bracing Pr
Research Area
Environment
Scheduled Completion Date
2016-03-31
Revised Completion Date
2016-06-30
Principal Investigator
Email Dahl, Peter
Research Manager
Email Brooks, Rhonda
Technical Monitor
 
Budget Number
63-6984
Impact Driving of Double Wall and Mandrel Piles at the Vashon Ferry Terminal, Vashon, Washington
Research Area
Environment
Scheduled Completion Date
2016-03-31
Revised Completion Date
 
Principal Investigator
Email Reinhall, Per
Research Manager
Email Brooks, Rhonda
Technical Monitor
 
Budget Number