Project Title Research Agency Reporting Period
A Weather Information System for Washington State-Phase III TRAC/University of Washington Jan 01, 2007 to Jun 30, 2007
Principal Investigator Agency Budget No. Agmt./Task No.
Mass, C. 66-7734 T2695-58
Other Investigator(s) Item No. Funding Source
  WSDOT SPR
WSDOT Program Manager Start Date Schedule Status
Brodin, D.
360.705.7972 BrodinD@wsdot.wa.gov
2003-12-01  
Technical Contact Estimated Completion Revised Completion
2005-04-30 2007-06-30
FHWA or Other Technical Contact Original Estimated Cost Revised Cost
Brower, M. $248,350.00 $773,362.00
Research Area % Funds Expended % Work Completed
Traffic & Intelligent Transportation Systems Evaluation    
Objective

To provide comprehensive weather information that will both help WSDOT maintain its roadways and help the public travel more safely.

Project Progress

New Period Proposed Activity

Problems

Implementation and Other Relevant Information