| Project Title | Research Agency | Reporting Period |
|---|---|---|
| Optimal Timing and Design for Bituminous Surface Treatments | TRAC/University of Washington | |
| Principal Investigator | Agency Budget No. | Agmt./Task No. |
|
Mahoney, J. P.
206.685.1760
jmahoney@u.washington.edu
|
||
| Other Investigator(s) | Item No. | Funding Source |
| WSDOT Program Manager | Start Date | Schedule Status |
|
Willoughby, Kim
360 705-7978
willouk@wsdot.wa.gov
|
2009-12-16 | |
| Technical Contact | Estimated Completion | Revised Completion |
| 2011-06-30 | ||
| FHWA or Other Technical Contact | Original Estimated Cost | Revised Cost |
| $80,000.00 | ||
| Research Area | % Funds Expended | % Work Completed |
| Construction Maintenance & Materials | ||
| Objective | ||
|
The three major goals for this study of BSTS are: Goal 1: Develop a recommendation for WSDOT as to the optimal time for placing BSTs on HMA overlays and BSTs on BSTs. Goal 2: Complimentary to Goal 1 is to examine how high ADT levels can be for application of WSDOT BSTs. This has been discussed at prior BST workshops but needs further refinement. Goal 3: Fully investigate and recommend a BST design method for use by WSDOT. Evidence to date suggests that adaptation of an existing method (most likely McLeod) would be sufficient. |
||
| Project Progress | ||
| New Period Proposed Activity | ||
| Problems | ||
| Implementation and Other Relevant Information | ||