| Project Title | Research Agency | Reporting Period |
|---|---|---|
| BE-LOGIC | TRAC/University of Washington | |
| Principal Investigator | Agency Budget No. | Agmt./Task No. |
|
McCormack, E. D.
206.543.3348
edm@u.washington.edu
|
||
| Other Investigator(s) | Item No. | Funding Source |
| Research Centre of the Athens University of Econ | ||
| WSDOT Program Manager | Start Date | Schedule Status |
|
Zevgolis, Dimitris
|
2009-11-01 | |
| Technical Contact | Estimated Completion | Revised Completion |
| 2010-01-31 | ||
| FHWA or Other Technical Contact | Original Estimated Cost | Revised Cost |
| $14,494.00 | ||
| Research Area | % Funds Expended | % Work Completed |
| Objective | ||
|
The BE-LOGIC sub-contract will inventory US transport logistic policies. This effort will be completed in six tasks, with the level of effort in hours for each. |
||
| Project Progress | ||
| New Period Proposed Activity | ||
| Problems | ||
| Implementation and Other Relevant Information | ||