| Project Title | Research Agency | Reporting Period |
|---|---|---|
| Evaluation of Gussett Plate Connections in Steel Truss | TRAC/University of Washington | Jan 01, 2009 to Jun 30, 2009 |
| Principal Investigator | Agency Budget No. | Agmt./Task No. |
|
Berman, Jeffrey
206 616-3530
jwberman@u.washington.edu
|
63-5352 | T4118-44 |
| Other Investigator(s) | Item No. | Funding Source |
|
Roeder, C. W.
206.543.6199
croeder@u.washington.edu
|
FHWA | |
| WSDOT Program Manager | Start Date | Schedule Status |
|
Willoughby, Kim
360 705-7978
willouk@wsdot.wa.gov
|
2008-12-01 | On schedule |
| Technical Contact | Estimated Completion | Revised Completion |
|
Coffman, H.
360.570.2556
coffmah@wsdot.wa.gov
|
2009-11-30 | 2010-04-30 |
| FHWA or Other Technical Contact | Original Estimated Cost | Revised Cost |
|
Brecto, B.
360.753.9482
Barry.Brecto@fhwa.dot.gov
|
$100,000.00 | $115,000.00 |
| Research Area | % Funds Expended | % Work Completed |
| Bridges & Structures | 51.68% | 50.00% |
| Objective | ||
|
This study will use the FHWA Guide to load rate the connection capacity using advanced finite element analysis and attempt to develop prioritization techniques to identify critical checks that could be used to identify critical gusset connections. Furthermore, this study will specifically determine the proper values for unbraced length and buckling coefficient for plates in compression, as well as the necessary plate stiffness requirements to allow the development of the plastic resistance in shear. The new approach should enable bridge engineers to evaluate the capacity of gusset plates with near critical demand-to-capacity ratios to be identified for further, more refined, analysis and/or retrofit. |
||
| Project Progress | ||
|
Detailed finite element models of selected WSDOT gusset plates have been developed and more are continuing to be developed. Key parameters that impact the stress state of the gussets have been identified. Currently, a study is being conducted to determine the impact of those parameters. A preliminary methodology for simplified gusset evaluation has been conceived and the results of the parametric analysis will be used assess the method's adequacy over the coming months. Task 1 is continuing as additional WSDOT gusset plates of interest are identified.
|
||
| New Period Proposed Activity | ||
|
No new activity is proposed. |
||
| Problems | ||
|
No problems have been identified. |
||
| Implementation and Other Relevant Information | ||
|
No implementation of results has occurred yet. |
||
