Project Title Research Agency Reporting Period
Evaluation of Gussett Plate Connections in Steel Truss TRAC/University of Washington Jan 01, 2009 to Jun 30, 2009
Principal Investigator Agency Budget No. Agmt./Task No.
Berman, Jeffrey 63-5352 T4118-44
Other Investigator(s) Item No. Funding Source
Roeder, C. W.   FHWA
WSDOT Program Manager Start Date Schedule Status
Willoughby, Kim
360 705-7978 willouk@wsdot.wa.gov
2008-12-01 On schedule
Technical Contact Estimated Completion Revised Completion
Coffman, H.
360.570.2556 coffmah@wsdot.wa.gov
2009-11-30 2010-04-30
FHWA or Other Technical Contact Original Estimated Cost Revised Cost
Brecto, B. $100,000.00 $115,000.00
Research Area % Funds Expended % Work Completed
Bridges & Structures 51.68% 50.00%
Objective

This study will use the FHWA Guide to load rate the connection capacity using advanced finite element analysis and attempt to develop prioritization techniques to identify critical checks that could be used to identify critical gusset connections. Furthermore, this study will specifically determine the proper values for unbraced length and buckling coefficient for plates in compression, as well as the necessary plate stiffness requirements to allow the development of the plastic resistance in shear. The new approach should enable bridge engineers to evaluate the capacity of gusset plates with near critical demand-to-capacity ratios to be identified for further, more refined, analysis and/or retrofit.

Project Progress

Detailed finite element models of selected WSDOT gusset plates have been developed and more are continuing to be developed. Key parameters that impact the stress state of the gussets have been identified. Currently, a study is being conducted to determine the impact of those parameters. A preliminary methodology for simplified gusset evaluation has been conceived and the results of the parametric analysis will be used assess the method's adequacy over the coming months.

Task 1 is continuing as additional WSDOT gusset plates of interest are identified.
Task 2 is continuing. A modeling methodology has been developed and is being applied to the selected gusset plates.
Task 3 is continuing. As new gussets are selected the FHWA procedure is being applies.
Task 4 is continuing. As new gussets are identified, a range of parameters is studies for each.
Task 5 is continuing. A preliminary simplified methodology has been conceived and is now being evaluated against the various finite model results.
Task 6 (examples) is not yet underway.
Task 7 (reporting) is not yet underway.

New Period Proposed Activity

No new activity is proposed.

Problems

No problems have been identified.

Implementation and Other Relevant Information

No implementation of results has occurred yet.

Fri Jul 24 09:27:26 -0700 2009