Project Title Research Agency Reporting Period
Seismic Assessment and Retrofit of WSDOT Bridges with Prestressed Hollow Core Piles and Multiple TRAC/Washington State University Jan 01, 2009 to Jun 30, 2009
Principal Investigator Agency Budget No. Agmt./Task No.
Cofer, William
509.335.3232 wcofer@wsu.edu
13A-3815-5200 T4120-07
Other Investigator(s) Item No. Funding Source
ElGawady, Mohamed
509.335.1927 melgawady@wsu.edu
   
WSDOT Program Manager Start Date Schedule Status
Willoughby, Kim
360 705-7978 willouk@wsdot.wa.gov
2007-08-16 On schedule
Technical Contact Estimated Completion Revised Completion
Khaleghi, Bijan
360-705-7181 khalegb@wsdot.wa.gov
2009-08-15  
FHWA or Other Technical Contact Original Estimated Cost Revised Cost
$149,959.00
Research Area % Funds Expended % Work Completed
Bridges & Structures 84.10% 97.00%
Objective

Project Progress

All tasks are completed except Task 5, which is the submission of the final report.

New Period Proposed Activity

The draft final report will be completed and submitted within the next few weeks.

Problems

None

Implementation and Other Relevant Information

Results have been presented to WSDOT engineers.

Thu Jul 09 10:11:23 -0700 2009